Full Article Attached Extra Two Weeks Added to 1.3 Beta Cycle

Friday December 27th, 2002

Asa Dotzler has posted an update to the Mozilla 1.3 Beta schedule to netscape.public.mozilla.seamonkey. The target freeze date has been moved back two weeks to Tuesday 22nd January, shifting the ideal release date of Mozilla 1.3 to Thursday 21st February. See the updated Roadmap for more details.


#11 Re: Re: More Details

by asa <asa@mozilla.org>

Saturday December 28th, 2002 10:51 PM

You are replying to this message

Sudden realization? We had planned to pad beta with 10 days or 2 weeks well before alpha was even released and some key stakeholders were already aware of this. I just suck at getting timely information out.

--Asa